Lifecycle service

Migrate & Transform

Infrastructure transitions require methodical planning and flawless execution.

The challenge

Migrations are high-stakes operations with asymmetric consequences. Success is invisible: systems work, business continues, nobody notices. Failure is catastrophic: downtime, data loss, regulatory exposure.

The complexity is often underestimated. A data center migration is not just moving equipment; it is coordinating dependencies across applications, networks, storage and facilities while maintaining operations. A cloud migration is not just lifting workloads; it is re-architecting for a different operational model while both environments must function. Lease expirations, budget cycles and data-movement regulations compound the difficulty. The organizations that succeed treat migration as a program, not a project.

How we work

Migration success starts with discovery. What actually exists? Not what is documented or assumed, but what is running, connected and dependent on what. We have found production systems on hardware supposedly decommissioned years ago and critical applications with undocumented dependencies.

Planning translates discovery into executable sequences: what moves when, which dependencies must be satisfied before each wave, what rollback exists if something fails. Execution combines discipline with adaptability, with real-time communication and post-migration validation that confirms what was supposed to happen actually happened. Our teams have moved 250+ applications and managed international logistics with zero unplanned downtime.

FAQ

Frequently asked questions

What is the difference between over-the-wire and forklift migrations?

Over-the-wire moves data and applications across network connections. Forklift physically relocates equipment. Many migrations combine both depending on equipment, timeline and cost.

How do you maintain operations during migration?

Waves are designed around operational requirements: critical systems move in maintenance windows, redundant systems one component at a time with validation between moves. Our Portland project migrated 250 applications with zero unplanned downtime.

Do you handle international migrations?

Yes. Our Silicon Valley to Iceland project moved 17,000 assets across three countries in 14 days including customs coordination and multi-jurisdiction data handling compliance.

How do you handle application dependencies?

Dependency mapping combines documentation review, automated discovery and stakeholder interviews. Waves are sequenced so that when an application moves, everything it needs is already at the destination or still accessible at the source.

What is your approach to rollback?

Every plan includes rollback procedures verified before any cutover. For critical systems we often keep the source environment rollback-ready for a defined period after migration.

Do you support hybrid and multi-cloud?

Yes. The key is ensuring the end state is manageable, not just achievable.

Migrations don’t have to mean downtime.

Let’s plan yours.