Portland: Full-Facility Migration Under Deadline Pressure
80,000 sq ft migrated, 250 applications moved—5 days ahead of six-figure penalty deadline.
80,000
Square Feet
250
Applications
60 DAYS
Project Execution
5 DAYS
Ahead of Schedule
The Challenge
The client faced a hard deadline with significant financial consequences: vacate an 80,000 square foot facility or face six-figure penalties. The scope extended far beyond simple equipment relocation—250 applications needed to migrate to a new environment, and the destination facility required custom build-out before it could receive the infrastructure.
The timeline left no room for sequential execution. Assessment, build-out, migration, and decommissioning would need to overlap, with precise coordination to ensure that dependencies were satisfied and operations continued throughout. A single missed handoff could cascade into deadline failure.
Adding complexity, the migration couldn’t disrupt ongoing business operations. Critical systems needed to remain available throughout the transition, with cutover windows carefully planned and communicated to stakeholders across the organization.
Our Approach
BNS Networks managed the engagement as an integrated program spanning three lifecycle phases simultaneously. While build-out crews prepared the destination facility, migration teams documented dependencies and planned application cutover sequences. Decommissioning protocols were established in advance so that source infrastructure could be retired immediately after successful migration validation.
The program operated with clear accountability and continuous communication. Daily standups identified blockers before they became delays. Risk registers tracked potential issues with mitigation plans ready. The aggressive timeline demanded discipline—but also flexibility when conditions required adjustment.
Work Undertaken:
- Custom build-out of destination facility
- Dependency mapping for 250 applications
- Phased application migration with validation
- Physical infrastructure relocation
- 80,000 sq ft facility decommissioning
- Certified data destruction
- Space restoration to original condition
Technologies & Standards:
- NIST SP 800-88 compliant data destruction
- Application dependency mapping
- Phased migration methodology
