Data centers · AI/GPU
10 MW of AI infrastructure. 400 racks. 16 weeks.
Design through commissioning with zero safety incidents and zero callbacks.
At a glance
The challenge
A Fortune 500 gaming technology company needed to rapidly deploy AI infrastructure for next-generation game development and real-time rendering. The project required unprecedented density, 40 kW per rack across approximately 400 cabinets, on a timeline traditional approaches could not meet.
The client also operated under gaming commission oversight requiring enhanced physical security. Standard colocation security would not satisfy audit requirements; the infrastructure needed to be isolated, monitored and access-controlled to standards more typical of financial services or classified government facilities. Delays would hit product development timelines with substantial downstream consequences.
Our approach
BNS Networks served as prime contractor, self-performing across all trades to maintain quality control and eliminate the coordination gaps that plague multi-vendor deployments. When a single organization owns design, installation and commissioning, accountability is clear and handoff problems disappear.
Our team began with detailed power and cooling assessments, modeling thermal loads for GPU infrastructure that generates heat densities far beyond traditional IT. The liquid cooling design integrated with the facility’s existing air handling, augmenting rather than replacing conventional cooling. Cage construction and physical security proceeded in parallel with power distribution and cooling, without sacrificing methodical verification.
Outcomes
What the client got
- 10 MW of AI compute infrastructure fully operational
- ~400 racks of NVIDIA H100/H200 deployed and configured
- Direct-to-chip liquid cooling supporting 40 kW per rack
- Zero safety incidents through construction and commissioning
- Zero callbacks or punch list items at handover
- Gaming commission security audit passed on first review
- Ongoing smart hands support contract awarded
More
Related case studies
Hillsboro OR: 2.5 MW data center
2.5 MW greenfield data center with 25 RPPs and Hot Aisle Containment, from empty shell to operational in 6 weeks.
Read the case studyBlanchard ID: fiber-to-the-home
Fiber-to-the-home deployment for an underserved community, 120 days from federal grant award to operational network.
Read the case studySempra Energy: Azure migration
Azure migration that cut deployment from months to days, eliminated PUC fines and delivered $1M+ savings per refresh cycle.
Read the case studyPlanning an AI infrastructure deployment?
Let’s discuss your requirements.