Real projects, real numbers. What we were asked to do, how we did it, and what the client got.

Data centers · AI/GPU

Austin TX: 10 MW AI infrastructure

10 MW AI infrastructure with ~400 racks of NVIDIA H100/H200 and direct-to-chip liquid cooling, design through commissioning in 16 weeks.

Read the case study
Data centers · Build-out

Hillsboro OR: 2.5 MW data center

2.5 MW greenfield data center with 25 RPPs and Hot Aisle Containment, from empty shell to operational in 6 weeks.

Read the case study
Telecommunications · Fiber

Blanchard ID: fiber-to-the-home

Fiber-to-the-home deployment for an underserved community, 120 days from federal grant award to operational network.

Read the case study
Enterprise · Cloud migration

Sempra Energy: Azure migration

Azure migration that cut deployment from months to days, eliminated PUC fines and delivered $1M+ savings per refresh cycle.

Read the case study
Enterprise · Migration

Portland OR: full-facility migration

80,000 sq ft facility decommissioned, 250 applications migrated and a new location built out, completed 5 days ahead of a six-figure penalty deadline.

Read the case study
Data centers · International

Silicon Valley to Iceland

Decommissioned a 7,500 sq ft colocation suite with 17,000 assets across three countries in 14 days, with NIST-compliant destruction and asset value recovery.

Read the case study
Enterprise · ITAD

Northern Virginia: multi-site decommission

Multi-site enterprise decommissioning across the Northern Virginia region with NIST-compliant destruction and a complete audit trail.

Read the case study
Enterprise · ITAD at scale

WeWork: 1,800 locations

Coordinated IT asset disposition across 1,800 locations during Chapter 11 restructuring: 100,000+ assets, PCI-DSS and SOX compliance, zero data incidents.

Read the case study
Data centers · Cloud migration

Groupon: 21,000 servers, 3 data centers

Position-level decommissioning of 21,000 servers across Sacramento, Dublin and Ashburn during a parallel cloud migration, with SOX and GDPR compliance and zero production impact.

Read the case study